N1 Project — Periodic maintenance of National Route 1, Section 17
The South African National Roads Agency SOC Limited (SANRAL): periodic maintenance of National Route 1 Section 17, from Westleigh (km 77.80) to Heuningspruit (km 101.30) — 23.6 km in total. The project is in the Free State, in the Fezile Dabi District Municipality and Moqhaka Local Municipality. Approximate duration is 18 months, including a 3-month mobilisation period.
Scope of works
- Surface repairs
- Milling of existing UTFC (25–30 mm). Areas showing surface failures are milled to a depth of 50 mm and replaced with 50 mm continuously graded asphalt.
- Base repair
- Bitumen Stabilised Materials (BSM1): in-situ recycled to a depth of 150 mm to BSM1 quality (2% SS60 and 1% cement).
- Texture slurry
- A fine texture slurry applied to the entire carriageway once all surface and base repairs are complete.
- Surface seal
- A 20/7.1/7.1 split seal using an S-E1 penetration binder.
Ancillary road works
- Non-structural gabions
- Installation of kilometre markers
- Road restraint systems
- Road signs
- Road markings and road studs